This set of Total Quality Management TQM Multiple Choice Questions & Answers (MCQs) focuses on Total Quality Management Set 8

Q1 | ______________ diagram is used for identifying potential relationship between twovariables.
Q2 | Lots for acceptance sampling should be ______________ and ______________.
Q3 | The roof of house of quality shows the interrelationship between:
Q4 | X bar charts are uses to control the ______________ of a process.
Q5 | Given that for the three samples, the value of R bar is .66 and value of d2 corresponding tothree is1.128, what is the estimated standard deviation?
Q6 | Given L=3 and p=.03, estimate the sample size that can be used for construction of a pchart.
Q7 | The chart used for tracking number non-conforming is:
Q8 | For a c chart, the OC curve plots the ______________ against ______________.
Q9 | Identification of customers and listening to the Voice of Customer (VoC) are a part of:
Q10 | Ease of repair is associated with ______________ dimension of quality.
Q11 | SIPOC diagram, used for understanding the flow in a process is used in ______________stage of DMAIC.
Q12 | Two major components of fitness of use are Quality of Design and ______________.
Q13 | For new product development, the chosen methodology should be
Q14 | In DMAIC, redesigning of process to either remove bottlenecks or to reduce waste takesplace in the ______________ stage.
Q15 | The critical path method determines the ______________ path from the beginning to theend of the project.
Q16 | The Operating characteristic curve shows the relationship between the probability ofacceptance (on y axis) and ______________ (on x axis).
Q17 | In a double sampling plan, let d1 be the number of defects in the first sample and d2 be thenumber of defects in the second sample. Let c2 be the acceptance number for both samples. The condition for rejection is:
Q18 | While random variability in a system can be removed by ______________, non-randomvariability requires ______________.
Q19 | The concept of rational sub group means that subgroups or samples be selected such that ifassignable causes are present the chances for differences between subgroups will be ______________.
Q20 | Q-Q plot is used to check:/p>
Q21 | The OC curve provides a measure of the ______________ of the control chart.
Q22 | Which of the following is not a type of attribute chart?
Q23 | The thickness of aluminum sheet is specified to be of 6±2 mm. The Upper SpecificationLimit and Lower Specification Limit for the sheet are:
Q24 | Failure Mode and Effects Analysis, which prioritizes different sources of error, is used in______________ stage.
Q25 | In a six sigma improvement project the least experienced individuals are: