On This Page
This set of Software Project Management (SPM) Multiple Choice Questions & Answers (MCQs) focuses on Software Project Management Set 11
Q1 | A software provides the framework from which a comprehensive plan for software development can be established.
- people
- product
- process
- none of the mentioned
Q2 | Who defines the business issues that often have significant influence on the project?
- practitioners
- project managers
- senior managers
- none of the mentioned
Q3 | Who delivers the technical skills that are necessary to engineer a product or an application?
- practitioners
- project managers
- senior managers
- none of the mentioned
Q4 | Which of the following paradigm attempts to structure a team in a manner that achieves some of the controls associated with the closed paradigm but also much of the innovation that occurs when using the random paradigm?
- asynchronous paradigm
- open paradigm
- closed paradigm
- synchronous paradigm
Q5 | Which of the following is a people- intensive activity?
- problem solving
- organization
- motivation
- project management
Q6 | Which paradigm structures a team loosely and depends on individual initiative of the team members?
- random paradigm
- open paradigm
- closed paradigm
- synchronous paradigm
Q7 | Which of the following is not an approach to software cost estimation?
- empirical
- heuristic
- analytical
- critical
Q8 | Which paradigm relies on the natural compartmentalization of a problem and organizes team members to work on pieces of the problem with little active communication among themselves?
- random paradigm
- open paradigm
- closed paradigm
- synchronous paradigm
Q9 | Who interacts with the software once it is released for production use?
- end-users
- client
- project (technical) managers
- senior managers
Q10 | Which of the following is not an effective project manager trait?
- problem solving
- managerial identity
- influence and team building
- none of the mentioned
Q11 | Which type of software engineering team has a defined leader who coordinates specific tasks and secondary leaders that have responsibility for sub tasks?
- controlled decentralized (cd)
- democratic decentralized (dd)
- controlled centralized (cc)
- none of the mentioned
Q12 | Commitments to unrealistic time and resource estimates may result in
- project delay
- poor quality work
- project failure
- all of the mentioned
Q13 | Which software engineering team has no permanent leader?
- controlled decentralized (cd)
- democratic decentralized (dd)
- controlled centralized (cc)
- none of the mentioned
Q14 | Which of the following is not a project factor that should be considered when planning the structure of software engineering teams?
- the difficulty of the problem to be solved
- high frustration caused by personal, business, or technological factors that causes friction among team members
- the degree of sociability required for the project
- the rigidity of the delivery date
Q15 | Which of the following is a collection of project coordination technique?
- formal approaches
- formal, interpersonal procedures
- informal, interpersonal procedures
- all of the mentioned
Q16 | Which activity sits at the core of software requirements analysis?
- problem decomposition
- partitioning
- problem elaboration
- all of the mentioned
Q17 | Which of the following is not a sign that indicates that an information systems project is in jeopardy?
- software people don’t understand their customers needs
- changes are managed poorly
- sponsorship is gained
- users are resistant
Q18 | SPMP stands for
- software project manager’s plan
- software project management plan
- software product management plan
- software product manager’s plan
Q19 | Which of the following categories is part of the output of software process?
- computer programs
- documents that describe the computer programs
- data
- all of the mentioned
Q20 | 4 COST MONITORING
- baselines
- source code
- data model
- none of the mentioned
Q21 | Software Configuration Management can be administered in several ways. These include
- a single software configuration management team for the whole organization
- a separate configuration management team for each project
- software configuration management distributed among the project members
- all of the mentioned
Q22 | What combines procedures and tools to manage different versions of configuration objects that are created during the software process?
- change control
- version control
- scis
- none of the mentioned
Q23 | What complements the formal technical review by assessing a configuration object for characteristics that are generally not considered during review?
- software configuration audit
- software configuration management
- baseline
- none of the mentioned
Q24 | Which of the following is the process of assembling program components, data, and libraries, and then compiling and linking these to create an executable system?
- system building
- release management
- change management
- version management
Q25 | Which of the following option is not tracked by configuration management tools?
- tracking of change proposals
- storing versions of system components
- tracking the releases of system versions to customers
- none of the mentioned