This set of Software Project Management (SPM) Multiple Choice Questions & Answers (MCQs) focuses on Software Project Management Set 10
Q1 | A view shows the system hardware and how software components are distributed across the processors in the system.
- physical
- logical
- process
- all of the mentioned
Q2 | The UML was designed for describing
- object-oriented systems
- architectural design
- srs
- both object-oriented systems and architectural design
Q3 | Which of the following is an architectural conflict?
- using large-grain components improves performance but reduces maintainability
- introducing redundant data improves availability but makes security more difficult
- localizing safety-related features usually means more communication so degraded performance
- all of the mentioned
Q4 | Which of the following is not included in Architectural design decisions?
- type of application
- distribution of the system
- architectural styles
- testing the system
Q5 | Architecture once established can be applied to other products as well.
- true
- false
Q6 | Which of the following pattern is the basis of interaction management in many web- based systems?
- architecture
- repository pattern
- model-view-controller
- different operating system
Q7 | What describes how a set of interacting components can share data?
- model-view-controller
- architecture pattern
- repository pattern
- none of the mentioned
Q8 | Which view in architectural design shows the key abstractions in the system as objects or object classes?
- physical
- development
- logical
- process
Q9 | Which of the following is a type of Architectural Model?
- static structural model
- dynamic process model
- distribution model
- all of the mentioned
Q10 | Why is decomposition technique required?
- software project estimation is a form of problem solving
- developing a cost and effort estimate for a software project is too complex
- all of the mentioned
- none of the mentioned
Q11 | Cost and effort estimation of a software uses only one forms of decomposition, either decomposition of the problem or decomposition of the process.
- true
- false
Q12 | If a Direct approach to software project sizing is taken, size can be measured in
- loc
- fp
- loc and fp
- none of the mentioned
Q13 | Which software project sizing approach develop estimates of the information domain characteristics?
- function point sizing
- change sizing
- standard component sizing
- fuzzy logic sizing
Q14 | How many forms exists of Barry Boehm’s COCOMO Model?
- two
- three
- four
- no form exists
Q15 | Who suggested the four different approaches to the sizing problem?
- putnam
- myers
- boehm
- putnam and myers
Q16 | In many cases, it is often more cost- effective to acquire, rather than develop, computer software.
- true
- false
Q17 | A make-buy decision is based on whether
- the software may be purchased off-the- shelf
- “full-experience” or “partial-experience” software components should be used
- customer-built software should be developed
- all of the mentioned
Q18 | Which of the following is not one of the five information domain characteristics of Function Point (FP) decomposition?
- external inputs
- external outputs
- external process
- external inquiries
Q19 | The project planner must reconcile the estimates based on decomposition techniques to produce a single estimate of effort.
- true
- false
Q20 | Programming language experience is a part of which factor of COCOMO cost drivers?
- personnel factor
- product factor
- platform factor
- project factor
Q21 | If an Indirect approach is taken, then the sizing approach is represented as
- loc
- fp
- fuzzy logic
- loc and fp
Q22 | Project management involves the planning, monitoring, and control of the people, process, and events that occur as software evolves from a preliminary concept to an operational implementation.
- true
- false
Q23 | 2 COLLECTION OF DATA
- people
- product
- popularity
- process
Q24 | PM-CMM stands for
- people management capability maturity model
- process management capability maturity model
- product management capability maturity model
- project management capability maturity model
Q25 | Which of the following is not a project manager’s activity?
- project control
- project management
- project planning
- project design