Q1 | The standard dimensions of a wooden sleeper for a B.G. railway track are
Q2 | The limiting value of cant excess for Broad Gauge is
Q3 | Indian Railways detects the rail flow by
Q4 | The gradient on which an additional engine is required to negotiate the gradient, is called
Q5 | If D is distance between centres of two parallel tracks of gauge G with entire curved leads and equal angles of crossing, total length of crossover, is
Q6 | Which of the following mechanical devices is used to ensure that route cannot be changed while the train is on the point even after putting back the signal?
Q7 | Pot sleepers are used if degree of the curve does not exceed
Q8 | Burnettising is done for the preservation of
Q9 | Consider the following statements:Automatic signalling system results in1. Greater risk2. Higher efficiency3. Avoidance of block instruments4. Higher operating costOf these statements
Q10 | A kink is made in stock rails, ahead of the toe of switch at a distance of
Q11 | Rails are fixed on steel sleepers
Q12 | Largest dimension of a rail is its
Q13 | The rail section which is not used on Indian metre gauge tracks, is
Q14 | Advantage of automatic signalling, is:
Q15 | For developing thinly populated areas, the correct choice of gauge is
Q16 | Coning of wheels
Q17 | An extra 7.5 cm ballast width is not provided on outer side on a curve, if its degree is
Q18 | Standard size of wooden sleeper for Broad Gauge track is
Q19 | By interchanging gibs and cotters of a pot sleeper, gauge may be slackened by
Q20 | The main function of sleepers, is
Q21 | The limiting value of cant gradient for all gauges is
Q22 | The spike commonly used to fix rails to wooden sleepers in Indian railways, is
Q23 | Track construction involves preparation of
Q24 | Study the following statements regarding creep.(i) Creep is greater on curves than on tangent railway track,(ii) Creep in new rails is more than that in old rails,(iii) Creep is more on steep gradients than on level track. The correct answer is
Q25 | According to Indian Railway Board, no diamond crossing should be flatter than