Total Quality Management Set 9
On This Page
This set of Total Quality Management TQM Multiple Choice Questions & Answers (MCQs) focuses on Total Quality Management Set 9
Q1 | The ______________ diagram starts with one item which then branches of into two or moreitems. This diagram is used to breakdown broad categories into finer levels of detail.
- Affinity
- Tree
- Relations
- Matrix
Q2 | Lot tolerance percent defective (LTPD) is a level of lot quality specified by the______________.
- Consumer
- Producer
- Supplier
- Sampling Plan
Q3 | Machine wear and tear is ______________ source of variation.
- Random
- Natural
- Assignable
- Cannot be determined
Q4 | Pattern in control charts which show the tendency to cluster around central line is termed as:
- Stratification
- Mixture
- Cyclic pattern
- Shift in process level
Q5 | When output product of several sources is fed into a common stream, the pattern of thecontrol chart expected is:
- Stratification
- Trend
- Mixture
- Cyclic Pattern
Q6 | A fan blade is specified by length and thickness. While sampling, it was found that for one particular blade, the length was non-conforming while the thickness was as per specifications. Should the blade be considered non-conforming for construction of a p chart?
- Yes
- No
- none
- none
Q7 | Consider that for a particular process, the p has shifted to .4 and the process has gone out ofcontrol. The corresponding value of beta is found to be .3356. The value of Average Run Length is:
- 2.5
- 1.5 ((1/1-beta) provides us with average run length)
- 1.0
- 2.7
Q8 | Consider for a process in control, the value of alpha is .0015. What is the value of theaverage run length?
- 666 ( 1/alpha gives us an estimate of average run length)
- 555
- 444
- None of the above
Q9 | Identify the charts which might give an indication of process going out of control (beforethe process has actually changed)
- X bar and c
- P and c
- R and u
- X bar and R
Q10 | The four phases of the Shewart cycle are:
- Plan, Do, Scan, Implement
- Plan , Act , Do, Control
- Plan, Do, Act, Check
- Implement, Design, Control, Plan
Q11 | For a process which is six sigma complaint, the percentage of products within specificationsis:
- 95.20%
- 99.73%
- 99.10%
- 96.78%
Q12 | Mistake proofing of process is done in the ______________ stage of DMAIC.
- Define
- Measure
- Improve
- Control
Q13 | In ______________ step of Quality Function Deployment, product or service requirementsare collected and analyzed through techniques like market research.
- Identify Customer Attributes
- Identify Design Attributes / Requirements
- Conduct an Evaluation of Competing Products.
- Evaluate Design Attributes and Develop Targets
Q14 | For a double sampling plan the probability of acceptance on the combined samples iscalculated as:
- Maximum of probability of acceptance of first and second sample
- Product of probability of acceptance of first and second sample
- Average of probability of acceptance of first and second sample
- Sum of probability of acceptance of first and second sample
Q15 | ______________ can be defined as small subset of a lot.
- Defect
- Fraction Acceptable
- Sample
- Acceptance Number
Q16 | If the value of D4 = 2.547, D3=0, then what is the UCL and LCL for the R chart?
- UCL=1.5, LCL=.4
- UCL= 1.2, LCL=.2
- UCL=1.5, LCL=0
- UCL=1.6, LCL=0
Q17 | Process capability ratio is expressed as:
- USL+LSL/6σ
- USL-LSL/6σ
- USL-LSL/3σ
- USL-LSL/σ
Q18 | Which of the following is the correct combination of specifications while designing acontrol chart?
- Sample size, Frequency of sampling, specification limit
- Sample size, Frequency of sampling, Number of defects
- Sample size, Specification limit, process standard deviation
- Sample size, Process mean, specification limit
Q19 | For a c chart, the LCL comes out to be -.7. The value of LCL that should be used is:
- -.7
- 0
- 1
- None of the above
Q20 | For a Poisson distribution:
- The mean is greater than the variance
- The mean is less than variance
- The mean is equal to the variance
- Cannot be determined
Q21 | Effective quality control results in:
- Increase in customer satisfaction
- Lower cost
- None of the above
- Both a and b
Q22 | Effective quality improvement can be instrumental in:
- Increasing productivity
- Reducing cost
- Both a and b
- None of the above
Q23 | Typically in a cause and effect diagram, the ______________ is used for classification ofcauses in the service industry.
- 5Ms
- 8Ps
- 5Ss
- 6Ps
Q24 | Producers risk can be defined as:
- The probability of rejecting a good lot
- The probability of accepting a bad lot
- The probability of accepting a good lot
- The probability of rejecting a bad lot
Q25 | In critical path method, earliest start is the:
- The largest Earliest Finish leading to that task
- The smallest Earliest Finish leading to that task
- Average of Earliest Finish leading to that task
- Whenever the task can start