On This Page
This set of Process Planning and Cost Estimation Multiple Choice Questions & Answers (MCQs) focuses on Process Planning And Cost Estimation Set 7
Q1 | Jigs And fixture are used to provide interchangeability.
- true
- false
Q2 | With the use of Jigs and fixture quality control expenses will
- reduce
- increases
- jigs and fixture are not used in any production process
- none of the mentioned
Q3 | With the use of Jigs and fixture
- labour cost decreases
- labour cost increases
- none of the mentioned
Q4 | Which of the following is not correct about fixture?
- it is used to hold the work
- it is used to position the work the work
- it assures high accuracy of parts
- it is used to guide the cutting tool
Q5 | Which of the following is not correct about jig?
- it is used to hold the work
- it is used to position the work the work
- it is used to guide the cutting tool
- none of the mentioned
Q6 | In which of the following operation jigs are preferred over fixture?
- drilling
- turning
- milling
- grinding
Q7 | Number of degree of freedom of a workpiece in space is equal to
- 10
- 12
- 14
- 16
Q8 | Land use, transportation and road network plans are
- inter linked
- intra linked
- not linked
- depends on the network
Q9 | What is the main cause of accidents in urban areas?
- improper planning
- extra wide roads
- additional thickness of the pavement
- traffic congestion
Q10 | The first stage in the function of traffic engineering department is?
- planning and design
- collection of data
- investigations
- finance
Q11 | Traffic forecast is not influenced by
- gdp
- industrial output
- population
- weather
Q12 | Demographic factors do not include
- gdp
- population in urban cities
- population in rural areas
- overall population
Q13 | The NHDP are being undertaken by private companies on the basis of
- profit
- revenue
- bot
- commission basis
Q14 | The traffic will increase if the
- price of fuel decreases
- price of vehicles decreases
- price of vehicles decreases
Q15 | The traffic population is estimated by
- arithmetic method
- geometric method
- incremental increase method
- harmonic method
Q16 | Which of the following data is not required to prepare an estimate?
- amplitude
- drawings
- specifications
- rates
Q17 | Estimating is the technique of calculating the various quantities and is needed for controlling the expenditure during the execution of the work.
- true
- false
Q18 | The process of working out the cost per unit of each item is known as
- work
- sheet
- data
- analysis
Q19 | While fixing rate per unit of an item, the quantity of materials and labour needed for one unit of an item are strictly per
- special data book
- standard data book
- special data record
- specific data record
Q20 | In the case of works which require some special types of equipment, an amount of
- 1-2
- 5-9
- 12-18
- 16-20
Q21 | Which of the following is not a method used for preparing approximate estimates?
- cubical contents method
- unit base method
- plinth area method
- cylindrical base method
Q22 | In the plinth area method, the cost of construction is computed by the multiplication of
- plinth length and rate
- plinth breadth and rate
- plinth area and plinth area rate
- plinth volume and plinth length rate
Q23 | As per IS 3861-1966, which of the following areas should not be included while calculating the plinth area of a building?
- porches of non-cantilever type
- area of barsati at terrace level
- area of walls at floor level
- area of lofts
Q24 | For the preparation of approximate estimates, cubical contents method is more accurate than the unit base method and plinth area method.
- true
- false
Q25 | In the cubical contents method, the cost of a structure is computed by the multiplication of total cubic contents and
- area of building
- volume of building
- local cubic rate
- length of building