Q1 | For the preparation of approximate estimates, cubical contents method is more accurate than the unit base method and plinth area method.
  • true
  • false
Q2 | In the cubical contents method, the cost of a structure is computed by the multiplication of total cubic contents and                
  • area of building
  • volume of building
  • local cubic rate
  • length of building
Q3 | Estimating is the technique of calculating the various quantities and is needed for controlling the expenditure during the
  • special data book
  • standard data book
  • special data record
  • specific data record
Q4 | is required for preliminary studies of various aspects of a work or project.
  • supplementary estimate
  • plinth area estimate
  • revised estimate
  • abstract estimate
Q5 | Approximate cost of a hostel building for 100 students @Rs.10000/- per student works out as Rs. 10 lakhs.
  • true
  • false
Q6 | Approximate cost of sewerage project for a population of one [email protected] Rs. 10/- head works out as Rs. 10 lakh.
  • true
  • false
Q7 | Cube rate estimate is less accurate as compared to the plinth area estimate as the height of the building is also compared.
  • false
  • true
Q8 | For storeyed building plinth area estimate is not prepared for each storey separately.
  • true
  • false
Q9 | is prepared on the basis of plinth area of building, the rate being deducted from the cost of similar building having similar specification, heights and construction, in the locality.
  • cube rate estimate
  • supplementary estimate
  • maintenance estimate
  • plinth area estimate
Q10 | In this method approx. total length of walls is found in running metre and this total length multiplied by the rate per running metre of wall gives a fairly accurate cost.
  • annual repair
  • item rate estimate
  • approximate quantity method estimate
  • cubical content estimate
Q11 | estimate is a detailed estimate and is prepared to maintain the structure or work in proper order and safe condition.
  • supplementary and revised estimate
  • maintenance estimate
  • item rate estimate
  • revised estimate
Q12 | The term is used to denote a procedure of costing or valuing an item of work on the basis of actual labourers and materials required.
  • prime cost
  • hour-work
  • day-work
  • sub-work
Q13 | Shaping of metal by squeezing them in between two or more dies in order to obtain desire shape is done by?
  • forming
  • forging
  • welding
  • grinding
Q14 | Which of the following is a type of forging?
  • open die
  • closed die
  • impression dies
  • hold dies
Q15 | In which of the following forging metal is kept in the lower die?
  • open die
  • closed die
  • impression dies
  • hold dies
Q16 | In which of the forging process metal is kept in between a pair of dies and a gutter is provided in the lower die?
  • open die
  • closed die
  • impression dies
  • hold dies
Q17 | The extra metal which settles down in the gutter is known as?
  • flash
  • slag
  • flux
  • barrelling
Q18 | In which of the following forging process no flash is formed?
  • open die
  • closed die
  • impression dies
  • hold dies
Q19 | Cogging, which is also called as drawing out, is basically?
  • open die forging operation
  • closed die forging operation
  • impression dies forging operation
  • hold die forging operation
Q20 | In rolling operation, the roll rotates with surface velocity?
  • exceeding the speed of incoming metal
  • lower than the speed of incoming metal
  • equal to speed of the incoming metal
  • very higher than the speed of incoming metal
Q21 | A round billet made of 70-30 brass is extruded at a temperature of 675°C. The billet diameter is 125 mm, and the diameter of the extrusion is 50 mm. Calculate the extrusion force required.
  • 4 mn
  • 5 mn
  • 5.6 mn
  • none of the mentioned
Q22 | In which type of extrusion, a billet is placed in a chamber?
  • forward
  • indirect
  • hydrostatic
  • impact
Q23 | In which type of extrusion, the die moves toward the unextruded billet?
  • forward
  • indirect
  • hydrostatic
  • impact
Q24 | In which type of extrusion, the billet is smaller in diameter than the chamber?
  • forward
  • indirect
  • hydrostatic
  • impact
Q25 | Scope of automation in foundry process is
  • low
  • high
  • minimum
  • maximum