This set of Management Science Multiple Choice Questions & Answers (MCQs) focuses on Management Science Set 3

Q1 | It ………. at which an activity can start.
  • est
  • eft
  • lst
  • lft
Q2 | ………… is the earliest starting time plus activity time.
  • est
  • eft
  • lst
  • lft
Q3 | ………. is the latest time by which an activity can be started without delaying thecompletion of the project.
  • est
  • eft
  • lst
  • lft
Q4 | ……….is the latest time by which an activity can be finished without delaying thecompletion of the project.
  • est
  • eft
  • lst
  • lft
Q5 | ……………is the duration by which an activity can be delayed without delaying theproject
  • slack
  • total float
  • free float
  • independent float
Q6 | ……… is the time by which the completion of an activity can be delayed beyond itsearliest finish time without affecting the earliest start time of a succeeding activity
  • slack
  • total float
  • free float
  • independent float
Q7 | ……….is activity oriented.
  • cpm
  • pert
  • lp
  • none of the above
Q8 | ………. is event oriented.
  • cpm
  • pert
  • lp
  • none of the above
Q9 | PERT emphasis on ………..
  • time
  • activity
  • a) and b)
  • none of the above
Q10 | Full form of PERT is
  • performance evaluation review technique
  • programme evaluation review technique
  • programme evaluation research technique
  • none of these.
Q11 | …….. is a scheme or design of something intended or device.
  • programme
  • project
  • network
  • float
Q12 | An activity which must be completed before one or more other activities start is knownas …………activity.
  • dummy
  • predecessor
  • successor
  • none of these
Q13 | The event is commonly represented by …… in network diagram
  • nodes
  • arrow
  • triangle
  • none of these
Q14 | …….is the disconnection of an activity before the completion of activities in a projectnetwork diagram.
  • dangling
  • looping
  • dummy
  • none of the above
Q15 | …………..is an activity oriented diagram.
  • cpm
  • pert
  • histogram
  • none of the above
Q16 | ………… is the duration by which an activity can be delayed without delaying theproject.
  • total float
  • slack
  • earliest event time
  • none of these
Q17 | ………is the shortest possible time in which an activity can be delayed withoutdelaying the project.
  • pessimistic time estimate
  • optimistic time estimate
  • most likely time estimate
  • none of these
Q18 | Which of the following is not a part of decision tree problem specification?
  • a list of alternatives
  • a list of possible state of nature
  • evpi
  • pay off associated with alternative/ state of nature combination.
Q19 | If a decision theory problem has 3 decision alternatives and 4 states of nature, thenumber of payoffs in that problem will be
  • 3
  • 4
  • 12
  • 64
Q20 | In a decision theory problem under complete uncertainty, which one of the followingapproaches will not be possible?
  • expected monetary value
  • maxmin
  • minimax
  • hurwicz
Q21 | For decision making under uncertainty, identify the decision rule that is appropriatefor the optimist.
  • laplace
  • maximax
  • minimax regret
  • maxmin
Q22 | What decision-making condition must exist for the decision tree to be a valuable tool?
  • certainty
  • uncertainty
  • risk
  • it does not matter, the tool is appropriate in all environments
Q23 | Which of the following is (are) types of decision-making environments?
  • decision making under uncertainty
  • decision making under certainty
  • decision making under risk
  • none of the above
Q24 | A good decision always implies that
  • will obtain the best final results
  • have used appropriate quantitative analysis.
  • have considered all alternatives
  • have followed a logical process.
Q25 | All of the following are steps in the decision-making process EXCEPT
  • define the problem
  • list alternatives
  • identify the possible outcomes
  • compute the posterior probabilities.