Q1 | The phase of System Development associated with creation of the test data is
  • system analysis
  • physical design
  • system acceptance
  • logical design
Q2 | Which of the following is not a named phase in the System development life cycle ?
  • assessment
  • maintenance
  • development
  • testing
Q3 | What is the final outcome of the requirements analysis and specifications phase ?
  • drawing the data flow diagram
  • the srs document
  • coding the project
  • the user manual
Q4 | QFD stands for
  • quality function design
  • quality function development
  • quality function deployment
  • none
Q5 | A Use-case actor is always a person having a role that different people may play.
  • true
  • false
Q6 | The user system requirements are the parts of which document ?
  • sda
  • srs
  • srr
  • rar
Q7 | What are the types of requirement in Quality Function Deployment(QFD) ?
  • known, unknown, undreamed
  • user, developer
  • functional, non-functional
  • normal, expected, exciting
Q8 | Traceability is not considered in Requirement Analysis.
  • true
  • false
Q9 | Which of the following statements about SRS is/aretrue ? i. SRS is written by customer ii. SRS is written by a developer iii. SRS serves as a contract between customer and developer
  • only i is true
  • both ii and iii are true
  • all are true
  • none of the above
Q10 | Risk management is one of the most important jobs for a
  • client
  • client
  • production team
  • project manager
Q11 | Which of the following risk is the failure of a purchased component to perform as expected?
  • product risk
  • project risk
  • business risk
  • programming risk
Q12 | Which of the following term is best defined by the statement: “There will be a change of organizational management with different priorities.”?
  • staff turnover
  • technology change
  • management change
  • product competition
Q13 | Which of the following term is best defined by the statement: “The underlying technology on which the system is built is superseded by new technology.”?
  • technology change
  • product competition
  • requirements change
  • none of the mentioned
Q14 | What assess the risk and your plans for risk mitigation and revise these when you learn more about the risk?
  • risk monitoring
  • risk planning
  • risk analysis
  • risk identification
Q15 | Which of the following risks are derived from the organizational environment where the software is being developed?
  • people risks
  • technology risks
  • estimation risks
  • organizational risks
Q16 | Which of the following risks are derived from the software or hardware technologies that are used to develop the system?
  • managerial risks
  • technology risks
  • estimation risks
  • organizational risks
Q17 | Which of the following term is best defined by the statement: “Derive traceability information to maximize information hiding in the design.”?
  • underestimate d development time
  • organizational restructuring
  • requirements changes
  • none of the mentioned
Q18 | Which of the following strategies means that the impact of the risk will be reduced?
  • avoidance strategies
  • minimization strategies
  • contingency plans
  • all of the mentioned
Q19 | Risk management is now recognized as one of the most important project management tasks.
  • true
  • false
Q20 | Choose the correct option according to the given statements regarding risk management.Statement 1: A risk is a potential problem—it might happen, it might not.Statement 2: Managers, software engineers, and customers participate in risk analysis and management. Statement 3: Only Managers participate in risk analysis and management.
  • statement 1and 2 are correct.
  • only statement 1 is correct.
  • only statement 3 is correct.
  • statement 1and 3 are correct.
Q21 | Reactive risk management is sometimes described as:
  • fire fighting mode
  • solution mode.
  • uncertain mode
  • none of the above.
Q22 | Software risk always involves two characteristics. What are those characteristics?
  • uncertainty and loss
  • certainty and profit
  • staff size and budget
  • project deadline and budget
Q23 | What is/are the different types of risk may occur when you develop software?
  • project risks
  • technical risks
  • business risks
  • all of the above
Q24 | Effective risk management plan needs to address which of these issues?
  • risk avoidance
  • risk monitoring
  • risk management and contingency planning
  • all of the above.
Q25 | Risk mitigation is a risk activity. Riskmonitoring is a activity
  • avoidance, project tracking.
  • increasing, project tracking.
  • project tracking, avoidance.
  • random, tracking.