Business Policy And Project Management Set 2
On This Page
This set of Business Policy and Project Management Multiple Choice Questions & Answers (MCQs) focuses on Business Policy And Project Management Set 2
Q1 | An Elaboration of Waterfall which stresses the necessity for validationactivities is known as __________.
- extended waterfall.
- iterative model.
- v-process model.
- spiral model.
Q2 | The spiral model is originated by __________.
- b.w.boehm.
- b.w.williams.
- b.w.britto.
- b.w.hackman.
Q3 | _______ is a working model of one or more aspects of the projectedsystem.
- evolutionary model.
- v-process model.
- spiral model.
- software prototyping.
Q4 | In Software Prototype, ___________ means copies of input screens areshown to the users on a workstation, but the screens cannot actually be used.
- simulation.
- annealing.
- mock-ups.
- rad system.
Q5 | In software prototype, partial working model is classified into ________.
- vertical and horizontal.
- vertical and straight.
- bended and horizontal.
- elevated and horizontal.
Q6 | SSADM means ___________.
- straight systems analysis design method.
- structured systems analysis design method.
- software systems analysis design method.
- solutions systems analysis design method.
Q7 | Which are the two levels of development suggested by Booch ?
- micro and macro processes.
- inter and intra processes.
- internal and external processes.
- small and large processes.
Q8 | 'Work expands to fill the time available" is _________ law.
- brooks.
- peters.
- parkinson\s.
- weinbergs
Q9 | The statement "Putting more people on a late job makes it later" is from_________ law.
- brooks.
- peters.
- parkinson\s.
- brokers.
Q10 | KLOC indicates ___________.
- hundred lines of code.
- source lines of code.
- thousand lines of code.
- million lines of code.
Q11 | Effort = __________.
- system size x productivity rate.
- system size x kloc.
- person in months / sloc.
- person in months x productivity rate.
Q12 | UFP indicates ________.
- unused function points.
- unstructured function points.
- uniform function points.
- unadjusted function points.
Q13 | PERT is _________.
- process evaluation and review technique.
- product evaluation and review technique.
- program evaluation and review technique.
- project evaluation and review technique.
Q14 | The activities have zero duration but are assumed to start at the same timeas the first and the end at the same time as the last one is called__________activity.
- hijacked.
- heuristic.
- hammocked.
- hole.
Q15 | _________ activities on the network diagram have zero duration and use noresources.
- dangling.
- dummy.
- null.
- zero.
Q16 | Every risk is associated with a likely problem and an _______.
- activity.
- outcome.
- action plan.
- threats.
Q17 | Risk Management consists of ____________.
- risk analysis and risk estimation.
- risk control and risk planning.
- risk identification and monitoring.
- risk control, planning, identification and monitoring.
Q18 | Ranking of the risks and determining risk aversion strategies is called_______.
- risk analysis.
- risk control.
- risk identification.
- risk evaluation.
Q19 | ________ = risk likelihood X risk impact.
- risk estimate.
- risk expenditure.
- risk identification
- risk exposure.
Q20 | Ranking of the risks and determining risk aversion strategies is called________.
- risk analysis.
- risk control.
- risk identification
- risk evaluation.
Q21 | The shortest time in which we could expect to complete the activity, barringoutright miracles are called ________.
- optimistic time.
- pessimistic time.
- most likely time.
- shortest time.
Q22 | Each activity has been scheduled to start at its earliest start date" is calledas_________.
- likelihood.
- activity schedule.
- probability.
- planning.
Q23 | In _________, the priority activities are allocated resources in ascendingorder of total. float.
- total free.
- total float.
- technical float.
- top float.
Q24 | _______ is an activity bar chart indicating scheduled activity dates anddurations frequently augmented with activity floats.
- bar chart.
- ball chart.
- slip chart.
- gantt chart.
Q25 | The priorities we might apply in deciding levels in monitoring is called as______.
- hierarchical monitoring.
- prioritized monitoring.
- tracking.
- tracing