Working with Tasks, Relationships, Constraints, and Milestones in Project 2016

Start No Earlier Than

Used for tasks that can only start after a certain date

Must Finish On

An Inflexible Constraint that overrides any task dependencies

As Soon As Possible

Does not determine when a task occurs and is based on task dependencies, durations and work times

As Late As Possible

Does not make allowances for any delays in the project

Finish No Later Than

Used for tasks that can only start after a certain date

Finish No Earlier Than

Ensures that a task finishes on or after a specified date

Which tab contains the command to add a milestone to the project plan

Task

Which tab enables you to add a recurring task in Project 2016?

Task

You have created a deadline reminder for a task that is now past its deadline.
How is this indicated in the Gantt chart?

A white exclamation point inside a red diamond in the indicator column

You want to configure two tasks so that work on one task overlaps the work on tis predecessor

Add lead time to the task

Identify methods used to delete tasks from a project plan

Left-click the task you wish to remove and press Delete on the keyboard
Right-click the task you want to remove and choose to delete it

Which statements describe how to add tasks to a project plan in Project 2016?

You can add new tasks at any time or rearrange existing tasks
The best way to add a task to the project plan is from Gantt Chart view
To add a task to a project plan, access Gantt Chart view and enter the task into the table