Work Management

Work Management means

the right components, the right time, the right components, and safely

Work Management process

makes sure it is safe for me to work on a component or equipment.

Work Management parts

makes sure I have the parts needed when I do the work

Work Management ensures

that when I identify something is broken it will be addressed.

Description of work management process

Identify, Screen, Plan, Schedule, Execute and Complete

Work Screening and Processing

first step of WM process

Work Screening and Processing descript

relies on your involvement, identifies safety concerns, requires a SRO to be involved, determined priority, assigns to approp group, determines the level of maintenance required

Screening results

work gets assigned to the right department

Screening results

work has been determined to be online or outage work

Screening results

priorities are assign to each Task A-C for passport (A highest) or 1 to 5 for PIMS (1 is highest)

Maintenance Planning

determines the details, develop work instructions, clearance orders are identified, parts identification and ordering, identify resources, define and plan support from other groups.

Cycle Plan

online work, based on a rolling 13 week interval over the course of a fuel cycle

System Availability

planning can bundle several work task together for when a system is out of service

E-20 establishes

risk managmenet reviews called PRA and insures we operate the plant safely, schedule development milestones or what has to happen when

E-0

week work is executed in

Right work validation

E-20, cycle manager and system engineers determine scope, work is selected based on the equipment reliability process, work is bundled with other preventive maintenance activities, work scope is developed based on available maintenance resources

E-15

scope freeze, work package planning begins, parts should be identified, resources required match resources available, any exceptions will have owners assigned

E15 thru E8

Coordinate any rescheduling, complete planning work packages by the end of E-10, prepare to freeze the schedule.

E10

Packages planned

E6

verify the job is ready for work, assign to appropriate work week manager

E6 the E2

task is assigned to specific crew, risk assessment reviews continue, operational conflicts are eliminated, RP coordinate enhanced planning if needed.

E3

schedule freeze, another risk assessment review, distribute frozen schedule to the work groups, departments now own schedule.

E1

preparation week, align or swap equipment, finalize briefings, equipment, staging

E+1

performance review week, review of performance indicators, identify any improvement opportunities or lessons learned

Passport and Pims

central database for planning, scheduling, and the completion of work orders

Passport and pims provide equipment info such as

location desired configuration and adjustable parameters