Chapter 7 proj mgmt

accountants usually define ____ as a resource sacrificed or foregone to achieve a specific objective or something given up in exchange

cost

what is the main goal of a project cost management

to complete a project within an approved budget

what are outputs of the project mgmt. process called "estimating costs" according to PMBOK

activity cost estimates, basis of estimates, project documents updates

if a company loses $5 for every $100 in revenue for a certain product, what is the profit margin for that product?

-5%

____ reserves allow for future situations that are unpredictable

management

you are preparing a cost estimate for a building based on its location, purpose, number of square feet and other characteristics. what cost estimating technique are you using?

parametric

____ involved allocating the project cost estimate to individual material resources or work items over time

project cost budgeting

___ is a project performance measurement technique that integrates scope, time and cost data

earned value management

If the actual cost for a WBS item is $1500 and its earned value is $2000, what is the cost variance, and is it under or over budget?

the cost variance is $500 and is under budget

if a project is halfway completed, its schedule performance index is 110 percent and its cost performance index is 95 percent, how is it progressing?

it is ahead of schedule and over budget

actual cost

the total of direct and indirect costs incurred in accomplishing work on an activity during a given period

analogous estimates

a cost estimating technique that uses the actual cost of a previous, similar project as the basis for estimating the cost of the current project; also called top down estimates

baseline

the original project plan plus approved changes

bottom up estimates

a cost estimating technique based on estimating individual work items and summing them to get a project total

budget at completion (BAC)

the total original budget for a project

budgetary estimate

a cost estimate used to allocate money into an organization's budget

cash flow analysis

a method for determining the estimated annual costs and benefits for a project

contingency reserves

dollar amounts included in a cost estimate to allow for future situations that may be partially planned for (sometimes called known unknowns) and that are included in the project cost baseline

cost baseline

a time phased budget that project managers use to measure and monitor cost performance

cost performance index (CPI)

the ratio of earned value to actual cost; can be used to estimate the projected cost to complete the project

cost variance (CV)

the earned value minus the actual cost

definitive estimate

a cost estimate that provides an accurate estimate of project costs

direct costs

costs that can be directly related to creating the products and services of the project

earned value (EV)

an estimate of the value of the physical work actually completed

earned value management (EVM)

a project performance measurement technique that integrates scope, time and cost data

estimate at completion (EAC)

an estimate of what it will cost to complete the project based on performance to date

indirect costs

costs that are not directly related to the products or services of the project, but are indirectly related to performing the project

intangible costs or benefits

costs or benefits that are difficult to measure in monetary terms

known unknowns

dollar amounts included in a cost estimate to allow for future situations that may be partially planned for (sometimes called contingency reserves) and that are included in the project cost baseline

learning curve theory

a theory that when many times are produced repetitively, the unit cost of those items normally decreases in a regular pattern as more units are produced

life cycle costing

the total cost of ownership, or development plus support costs, for a project

management reserves

dollar amounts included in a cost estimate to allow for future situations that are unpredictable (sometimes called unknown unknowns)

overrun

the additional percentage or dollar amount by which actual costs exceed estimates

parametric estimating

a cost estimating technique that uses project characteristics (parameters) in a mathematical model to estimate project costs

planned value (PV)

the portion of the approved total cost estimate planned to be spent on an activity during a given period

profit margin

the ratio between revenues and profits

profits

revenues minus expenses

project cost management

the processes required to ensure that the project is completed within the approved budget

rate of performance (RP)

ratio of actual work completed to the percentage of work planned to have been completed at any given time during the life of the project or activity

reserves

dollar amounts to be included in a cost estimate to mitigate cost risk by allowing for future situations that are difficult to predict

rough order of magnitude (ROM) estimate

a cost estimate prepared very early in the life of a project to provide a rough idea of what a project will cost

schedule performance index (SPI)

the ratio of earned value to planned value; can be used to estimate the projected time to complete a project

schedule variance (SV)

the earned value minus the planned value

sunk cost

money that has been spent in the past

tangible costs or benefits

costs or benefits that can be easily measured in dollars

top down estimates

cost estimating technique that uses the actual cost of a previous, similar project as the basis for estimating the cost of the current project; also called analogous estimates

unknown unknowns

dollar amounts included in a cost estimate to allow for future situations that are unpredictable (aka management reserves)